Several of Accion Senegal's projects are aimed at upgrading the facilities and infrastructure of the Primary School at Dialacoto.

In cooperation with the Education Committee, we decided that we needed to focus on the construction of the school's perimeter wall, for the sake of the students' security and safety.

The work started in mid-November 2010, and it was concluded on December 15th, 2010.

The wall is 240 metres long and 1,70 metres high.